Description

Time-line for Quiver cable chains per Jessica

Drawing issued to receipt of FA - 3 weeks
FA in house - 1 week
If changes need made to the chain - 2 weeks to correct and send back to us
2nd FA in house 1 week
2-3 weeks to get 10 Alpha/Beta units
4-ish weeks testing
PO to Igus for production qtys 1 week
Production to delivery at AM 4-6 weeks

Related Objects

Event Timeline

nickp created this task.Jun 6 2018, 9:27 AM
nickp triaged this task as Normal priority.
nickp created this object with edit policy "LulzBot Hardware Products (Project)".
west added a comment.Aug 23 2018, 3:48 PM

Cable chains were ordered as of 8/23/18

west added a comment.Sep 10 2018, 2:35 PM

We are still waiting on pricing

nickp raised the priority of this task from Normal to High.Sep 11 2018, 11:44 AM
nickp raised the priority of this task from High to Needs Triage.Sep 11 2018, 11:46 AM
west added a comment.Oct 22 2018, 4:28 PM

T4106 there will likely need to be a change to the x extruder harness depending on findings this friday

@tutley any progress on the cable chains that we were discussing yesterday? We need to get those figured out and to @jessica as soon as we can.

Steven added a subscriber: Steven.Nov 2 2018, 10:45 AM

Rented equipment arrived today to more rapidly confirm ESD mitigations. We should hopefully have better understanding my Monday.

Ah, good to hear! Thanks for the update

west added a comment.Nov 12 2018, 4:35 PM

The cable chains passed testing and look good. I did add some notes to the drawing to specify where the part number label should go and added some heatshrink to the jst side of the x motor to make it look a little nicer but no major changes

Steven closed this task as Resolved.Nov 20 2018, 2:33 PM

Closing this out. Parts will be released with the Alpha tag