Once I have plastic parts for these I was planing on generating MOs for the 10x of each mount that we will need for beta testing.

Related Objects

Event Timeline

adam created this task.Aug 21 2018, 9:17 AM
adam triaged this task as Normal priority.
adam created this object with edit policy "LulzBot Hardware Products (Project)".

two immediate questions:

  1. does production have the bandwidth right now to make these Betas?
  2. can the crimping machine handle all the operations necessary for these harnesses? There was some question if it could handle the female microfit.
kent added a subscriber: logan.Aug 21 2018, 9:25 AM
bowman reassigned this task from bowman to caguilar.Aug 21 2018, 2:12 PM
bowman closed this task as Resolved.
bowman added a subscriber: bowman.

@adam Yes, we will make the bandwidth to produce these Betas.
Transferring ticket to @caguilar Inventory control to set up routing and then we will procure MO's to produce the parts.
Then we can transfer parts to MER to complete the OHAI instructions and build completed beta adapter kits.

bowman reopened this task as Open.Aug 21 2018, 2:12 PM

@adam Do you know if the PP-GP0354 and 0355 have been approved for cluster production?

@caguilar a slice request has been created T3381 but we don't have approved slices for cluster yet. My understanding is that @EricNugent will be producing the beta printed parts and will have an approved slice after that process for production units.

adam added a comment.Sep 4 2018, 12:41 PM

okay - printed part slices are generated and ready to print.
BoMs are checked and updated to the no-switch version
I am procuring 15x of each to dock shipping - you can deliver them to me from there and put them in R&D for expensing.
@bowman do you need MER to complete a production OHAI before we can start these or can we have MER make the first one or two in order to generate the OHAI?

adam added a comment.Sep 4 2018, 12:48 PM

MR/2018/01334
MR/2018/01335

bowman added a subscriber: MichaelM.Sep 4 2018, 2:49 PM

Eric is going to print 15 each and then give them to Inventory to adjust into pre-sub. Pilot is building 15 each of the adapter cables on MO's for pre-sub.
Once those are completed and in pre-sub, Pre-sub / MER @MichaelM, @kent will complete the ohai and get them to @adam

adam added a comment.Sep 5 2018, 10:50 AM

@MichaelM @kent @bowman what are my chances of getting two of those TAZ mounts by the end of today? We would like two to verify the firmware we've generated and to show them off at IMTS next week (preview of coming attractions type of thing).

@adam @bowman I left the parts on Bowman's desk upstairs.

Kazkade added a subscriber: Kazkade.Sep 6 2018, 7:11 AM
alexei removed caguilar as the assignee of this task.Sep 7 2018, 7:28 AM
alexei removed a subscriber: caguilar.
adam closed this task as Resolved.Sep 20 2018, 10:33 AM
adam claimed this task.

Parts are at product planning - closing as resolved