kent created this task.Jun 5 2019, 8:46 AM
kent triaged this task as Normal priority.
kent created this object with edit policy "Restricted Project (Project)".
kent moved this task from Restricted Project Column to Restricted Project Column on the Restricted Project board.Jun 7 2019, 9:41 AM
kent moved this task from Restricted Project Column to Restricted Project Column on the Restricted Project board.Jun 7 2019, 10:09 AM

kent moved this task from Restricted Project Column to Restricted Project Column on the Restricted Project board.Jun 7 2019, 10:24 AM

kent moved this task from Restricted Project Column to Restricted Project Column on the Restricted Project board.Jun 7 2019, 12:13 PM
kent moved this task from Restricted Project Column to Restricted Project Column on the Restricted Project board.
kent removed kent as the assignee of this task.

Here is the final inspection report. This failed on insert/powdercoat order of operations (critical failure), and silk screen location. (non-critical failure).

kent assigned this task to jperry.Jun 21 2019, 2:14 PM

@jperry , the first article inspection for the Epocs mini 2 sheetmetal is complete. There are 6 tickets for these parts that I will assign to you now so you can send the reports to the supplier.

AOJAS added a subscriber: AOJAS.EditedJul 30 2019, 1:55 PM

Here is the report for the reworked PP-FP0147 that Epocs sent to us. The only remaining issue for Epocs to review and take action on is in regard to the silkscreen position(Dim 104 and 111) and silkscreen condition(Dim 101 and 112)). Since these are minor issues, these are being given "deviation granted" status, with the expectation that Epocs will act on the feedback in the attached pdf.